** This is a dynamic document and subject to change as the project progresses! **
| Contract signed [DONE] Server ordered [DONE] Implementation Team established [DONE] Begin work on migration questionnaire [DONE] Orientation visit to Endeavor headquarters [DONE] | |
| Sample data files extracted
[DONE] VTLS item map file completed [DONE] Server installed [DONE] Endeavor software installed and configured [DONE] Continue work on data migration questionnaire and mapping file [DONE] Data migration questionnaire completed [DONE] |
|
| Attend South Central Voyager Users Group meeting
[DONE] Continue to practice using training database Test extraction of data files to Endeavor [DONE] Draft of mapping file due [DONE] | |
| Functional training (November 8 - 11)
[DONE] Final mapping file due to Endeavor (November 8) [DONE] | |
| In-house training Final extraction of data due (December 13)[DONE] Test load of our full database (December 20)[DONE] |
|
| Final revised mapping file due (January 3)[DONE] Accept/reject test load - report (due January 4)[DONE] | |
| Cutoff for editing bib records on VTLS (April 1)[DONE] Attend Voyager User's Group Meeting (April 6-9) [DONE] Extract bibs and authorities for VTLS for WLN processing[DONE] Upgrade to Release 99.1 (April 20)[DONE] | |
| Second test load Test load report due |
|
| Close out 1999/2000 fiscal year on Innovative system Bib and authority records finished by WLN and sent to Endeavor |
|
| Production load of bibliographic/authority/holdings data Accept/reject production load Vendor record load Full back up Order record load Extract patron records Patron record load Accept/reject patron load |
|
| Extract fines/fees Fines/fees record load Extract circulation transactions Circulation transaction load LIVE IN ALL MODULES Begin 2000/2001 fiscal year on Voyager |